Project recovery points

Restore a whole project, all databases and stored files together, to an earlier point, and what happens to current data.

Updated Nov 12, 2026

A project recovery point captures every database in the project and all of its stored files at one moment.

Availability

The Project recovery points card on Databases > Backups appears only when recovery points are switched on for the platform. If it is missing, recovery points are not switched on. The first point is taken at the next scheduled backup after they are.

What you see

A table of Taken, Type (Scheduled, Manual, Before a restore), and Contents (databases and files with sizes). A summary shows how long ago the last point was taken. Incomplete points say Incomplete and cannot be restored by you.

Restore a project

  1. Choose Restore on a point. Only the project's owners see the button.
  2. In Restore this project?, choose parts: Databases, Stored files and optionally Sign-in users, API keys and secrets.
  3. Type the project name exactly to confirm, then choose Restore.

The project goes back to that moment; later changes are replaced. The current state is saved first as a recovery point, so a restore can be undone, and files added since are kept aside for a limited time. While restoring, a banner says so. Restores are rate-limited per hour, and one runs at a time.

Good to know